Availability

 

Are You Available?

 
 

The IndustryWeek Best Plants competition asks participants to share their average machine availability rate as a percentage of scheduled uptime. A higher percentage is better. Lower percentages or declining percentages can point to maintenance issues, scheduling issues or even workforce challenges. As the accompanying table indicates, IW Best Plants winners and finalists average more than 90% machine availability.

Average machine availability rate as a percent of scheduled uptime (%):
Year Median Average Minimum Maximum
2009 96.1 95.7 82.0 99.9
2010 95.0 92.1 61.2 99.9
2011 97.4 93.3 68.8 100.0
2012 95.5 94.1 77.0 99.9
2013 90.0 89.3 77.1 100.0
2009-2013 95.8 93.1 61.2 100.0

Source: 2013 IW Best Plants Statistical Profile